Three volume states
- Bank cubic yards (BCY)
- Volume of undisturbed material in the ground.
- Loose cubic yards (LCY)
- Volume after excavation, when the material is in a stockpile or truck.
- Compacted cubic yards (CCY)
- Volume after the material has been placed and compacted as fill.
Worked excavation example
A rectangular excavation is 75 ft long, 36 ft wide, and 4 ft deep. The material swells 25% when excavated and shrinks 10% when compacted, both relative to bank volume. Assume all material can be reused, with no losses. Each truck can carry 12 LCY, and volume governs its payload. Find the excavation volume, haul volume, minimum truck trips, and compacted fill yield.
1. Calculate the bank volume
75 ft × 36 ft × 4 ft = 10,800 ft³. Divide by 27 ft³ per yd³ to get 400 BCY.
2. Apply swell and calculate truck trips
400 BCY × 1.25 LCY/BCY = 500 LCY. Divide by 12 LCY per trip to get 41⅔ trips. Round up to 42 trips, with 8 LCY on the final trip.
3. Apply shrinkage to the bank volume
400 BCY × 0.90 CCY/BCY = 360 CCY. To go from loose directly to compacted volume in this example, multiply by 0.90 ÷ 1.25 = 0.72 CCY/LCY.
Try it yourself
A 54 ft × 25 ft excavation is 2 ft deep. The material has 20% swell and 5% shrinkage, both relative to bank volume. A truck holds 11 LCY. Assuming no material losses and a volume-limited payload, find the bank, loose, and compacted volumes and the minimum number of trips.
Show the solution
- 54 × 25 × 2 ÷ 27 = 100 BCY.
- 100 × 1.20 = 120 LCY.
- 100 × 0.95 = 95 CCY.